Compare the total agreed project scope before comparing headline prices. Two quotations can describe similar looking signs while leaving different costs and responsibilities with the customer.
Use the same photographs, intended sign size, opening target and description of the building. Ask each supplier to identify assumptions that need a survey. If one proposal includes illuminated letters and another a printed panel, treat them as different solutions until their scope is aligned.
| Line item | Question to resolve |
|---|---|
| Design and survey | How many design revisions are included and who confirms dimensions? |
| Manufacture | What substrate, lettering, finish and lighting system are specified? |
| Old sign removal | Are removal, disposal and making good included? |
| Installation access | Are lifting equipment, permits or out-of-hours visits allowed for? |
| Electrical scope | Who provides power and who completes any connection? |
| Commercial terms | Is VAT shown clearly and what triggers payment? |
| Aftercare | What is covered, for how long, and how are faults assessed? |
Use a simple reconciliation: quoted scope plus confirmed required extras equals the comparable project amount. Do not add invented allowances to make an incomplete quote look definite; ask the supplier to price the missing work.
For example, if one supplier includes removal and another excludes it, obtain the removal cost before choosing. This is a comparison method, not an estimate of local signage prices. Ask whether the price changes if the survey reveals unsuitable mounting conditions.
Record the final approval point and the start of the production period. Ask how artwork changes, additional visits and delays caused by unavailable access are handled. A date without its dependencies is difficult to use in an opening plan.
Avoid judging warranties by their duration alone. Check exclusions, installation coverage, repair access and the process for reporting a problem. Read the handover checklist alongside the quote. When obtaining a custom signage quotation, request an itemised scope that can be compared against the complete shopfront project.
Several comparable proposals can help, but a larger number is less useful if every supplier is pricing a different brief.
Ask for a specification before accepting it.
Not necessarily. First establish whether the scope, construction and service are comparable.
Ask for clear VAT treatment so your organisation can assess the actual payable amount and its own recovery position.
Request an itemised design manufacture and installation quotation. Explore SignCo’s custom signage or contact the team.